water utilitiesCritical priorityopen

Arlington Avenue Sewer Failure Phase II Loan

Toledo

Summary

Severe wet weather required extra temporary pumps during ongoing repairs to a collapsed 48-inch sewer main on Arlington Avenue, increasing project costs by $2 million. Council reviewed a supplemental loan from the Ohio Water Development Authority to cover the unexpected expenses.